Test sequence



- Switch off ignition.



- Connect socket box to component N3/10 (ME-SFI [ME] control unit).



- Connector F is plugged in at control unit.



- Unplug the socket F from the wiring harness at the socket box.



- Measure resistance with multimeter between sockets (F.41) 11 and (F.54) 24 of the 35-pole socket box tester.



Specified value



- Resistor[115...125]ohms



Question



- Is the measurement value OK?



YES



The measurement value is OK.End of test



NO



The measurement value is not OK.Possible cause and remedy



- Control unit N3/10 (ME-SFI [ME] control unit)



End of test



1.1.3.2.2. Voltage supply of engine compartment CAN control modules



Test 1.1.3.2.2.1: Check power supply at control unit A1 (Instrument cluster).



Test 1.1.3.2.2.2: Check power supply at control unit A89 (DTR controller unit).



Test 1.1.3.2.2.3: Check power supply at control unit N3/10 (ME-SFI [ME] control unit).



Test 1.1.3.2.2.4: Check power supply at control unit N15/3 (ETC [EGS] control unit).



Test 1.1.3.2.2.5: Check power supply at control unit N15/5 (Electronic selector lever module control unit).



Test 1.1.3.2.2.6: Check power supply at control unit N15/6 (Sprintshift control module).



Test 1.1.3.2.2.7: Check power supply at control unit N47-5 (ESP, SPS [PML] and BAS control unit).



Test 1.1.3.2.2.8: Check power supply at control unit N51 (AIRmatic with ADS control module).



Test 1.1.3.2.2.9: Check power supply at control unit N63/1 (DTR control module).



Test 1.1.3.2.2.10: Check power supply at control unit N71 (Headlamp range adjustment control module).



Test 1.1.3.2.2.11: Check power supply at control unit N73 (EIS [EZS] control unit).



Test 1.1.3.2.2.12: Check power supply at control unit N80 (Steering column module).



Test 1.1.3.2.2.13: Check power supply at control unit Y3/8n4 (Fully integrated transmission control (VGS) control unit).



1.1.3.2.2.1. Check power supply at control unit A1 (Instrument cluster).



Test prerequisites



- The fuses are OK.



- The power supply of the control unit N10/1 (Front SAM control unit with fuse and relay module) is OK.



Test sequence



- Switch off ignition.



- Detach the socket at component A1 (Instrument cluster).



- Measure direct voltage with multimeter between sockets (A1) 1 and (A1) 6



- Measure direct voltage with multimeter between sockets (A1) 2 and (A1) 6



- Measure direct voltage with multimeter between sockets (A1) 3 and (A1) 6



- Switch on ignition.



Specified value



- Voltage [11.0...14.5] V



Question:Is the measurement value OK?